
Benton
Utilities Civil Engineering Department
One
of the newer depts. at Benton Utilities is the Civil Engineering Dept. The
Construction Manager and Utilities inspector work closely with outside
engineering firms dealing with the planning, design, construction, and
maintenance of the utilities infrastructure. They deal primarily with the
water distribution and purification as well as the wastewater collections
and wastewater treatment plants.
The Construction Manager for Benton Utilities is Dewayne Hood; he came to
work here in 2006 having worked for an engineering firm prior to coming to
work here.
One
of many duties of our department includes periodic inspection and testing
of utilities being installed in new subdivisions and commercial projects.
Larry Lewis is the Utility inspector assigned to this job. The following
are just some of the subdivisions or projects that installed utilities in
the past year or so.
- Coldwater Creek
- Sterling Oaks
- Quail Valley
- The Woodlands
- Pleasant Forest
- Eden Estates
- BHS Soccer Fields
- West Shores at Hurricane Lake
In
spite of the slowing economy Benton continues to see many new homes being
built and new phases of subdivisions being added.
At the beginning of 2010 the Utility Locator position was reevaluated and
moved to our department. Josh Ramsey transferred from the water department
to take over this position. We currently process approximately 4500
utility locate tickets per year. Josh is responsible for locating the
city’s water and sewer mains along with the electrical infrastructure.
Please remember it is a state law to notify Arkansas One Call before you
dig. This call not only could save you money from avoided damage to a
utility line but more important could save your life.
Recent and Upcoming Projects:
Water Treatment Plant Clear Well Rehab
The rehab of a one million gallon clear well will begin in March of 2010.
The concrete tank will be drained so it can be cleaned and a new
protective lining applied to the interior. The project is expected to take
approximately 90 days to complete. The contractor for the project is
Protective Linings & Coatings, Inc. located in Alexander, AR. with an
anticipated cost of $ 123,401.00.
Almatis Water Line Project
Coakley
Company Inc. recently completed installing approximately 1060 linear feet
of 10” PVC water line off Alcoa Road. This project allowed Almatis Company
to begin buying water from Benton Utilities. All the construction cost for
this project was paid by Almatis.
Fema Phase II
Construction
has begun on the phase II portion of the fema project. This includes
repairs to the low water crossing on Brent Ford Road which allows access
to the water intake structure and a major sewer pump station. The crossing
was damaged during the flooding that occurred in 2008. The stabilization
of a sewer line crossing located north of Dyer Circle is also included as
part of the project. Construction for the project should be completed by
early summer.
Christy Acres Sewer Project
Construction
has been completed on the Christy Acres Sewer Project located south of
Market Street. This project allows sewer service to be available to an
area where many septic tanks were failing. A large portion of the project
was paid for by a grant for Arkansas Natural Resources. Kajacs Contractors
Inc. for Poplar Bluff, MO. was the contractor on the project.
Willow Street Sewer Pump Station Project
On-Line Construction, Inc. from Hot Springs, AR. has begun construction of
a new sewer pump station located on Willow Street. The new pump station
was designed to collect excess flows during rain events. The wastewater is
pumped the equalization basin located nearby and then returned to the
waste water treatment plant. This prevents overflows at the existing pump
station and provides a more consistent flow at the WWTP. Construction
should be completed by mid summer.
Waste Water Treatment Plant Expansion:
The
WWTP expansion was completed late in 2009. Max Foote Construction, Inc.
from Birmingham, AL. was the contractor for the project. This project
brings the design flow of the plant to 8.3 MGD with a peak flow of 12.5
MGD. The construction went very well completing the project two months
ahead of schedule and under budget.
|